Consider a situation where we have Process A that has fixed costs of $1000 and variable costs of $5 per unit; and Process B that has fixed costs of $500 and variable costs of $15 per unit. We also have Process C whose fixed cost is $1500 with $3/unit in variable costs. If you expect to sell 80 units of the product you can produce using any of the 3 processes, what is the best total cost of producing the 80 units using your best of the 3 processes?