CWN Company uses a job order costing system and last period incurred $79,000 of actual overhead and $100,000 of direct labor. CWN estimates that its overhead next period will be $76,000. It also expects to incur $100,000 of direct labor. If CWN bases applied overhead on direct labor cost, its predetermined overhead rate for the next period should be:________________.

Respuesta :

Answer:

76%

Explanation:

Predetermined overhead rate = estimated overhead / direct labor cost.

= $76,000 / $100,000

=76/100

=76%