Answer:
The correct answer is D.
Explanation:
Giving the following information:
Western Company allocates $10.00 overhead to each unit produced. The company uses a plantwide overhead rate with machine hours as the allocation base.
Estimated: Department 1 Department 2
Manufacturing overhead costs $250,000 $150,000
Machine hours 15,000 MH ?
We will sum the total overhead and divide it by the overhead rate. Doing this we will determine the total number of machine-hours.
Total machine-hours= 400,000/10= 40,000 hours
Department 2= total machine hours - department 1 machine hours
D2= 40,000 - 15,000= 25,000 machine hours