Answer:
$585,120
Explanation:
The computation of Budgeted direct labor costs is shown below:-
Direct labor cost per pod = Direct labor required per pod x Direct labor rate
= 2.4 × $10.60
= $25.44
Budgeted direct labor costs incurred in June = Direct labor cost per pod × Produced pods
= $25.44 × 23,000
= $585,120
Therefore for computing the budgeted direct labor costs we simply applied the above formula.