Answer:
Minimum People required = 5
Step-by-step explanation:
Total hours required to complete the work every week = 150 hrs.
Number of hours worked per week by one person = 32 hr
∴ Number of people required to complete the work per week = Total number of hrs to complete the work ÷ No of hrs work per person
∴ Number of people = 150 ÷ 32
∴ Number of people = 4.6875
This is the minimum number of people. But no of people cannot be a fraction.
Thus, rounding the number to next integer.
∴ Smallest number of people needed to complete the work = 5