Respuesta :
Answer:
Quik Furniture Company
The Sanding Department
Production Cost Report
For the month of March 2017:
Materials Conversion Total Costs
Cost of finished units $23,100 $52,500 $75,600
Ending Work in process 9,900 4,500 $14,400
Total Costs $33,000 $57,000 $90,000
Explanation:
a) Data and Calculations:
Finished and transferred out = 7,000 units
Units started but not completed:
Materials 3,000 100%
Conversion costs 600 20%
Equivalent units Materials Conversion Total Costs
Started and completed 7,000 7,000
Started but not completed 3,000 600
b) Computation of equivalent units:
Equivalent units 10,000 7,600
Costs: $33,000 $57,000 $90,000
Cost per equivalent unit $3.30 $7.5 $10.80
c) Calculation of costs:
Cost of finished units $23,100 $52,500 $75,600
Ending Work in process 9,900 4,500 $14,400
Total costs $33,000 $57,000 $90,000
d) The costs of finished units and Ending WIP for materials are obtained by multiplying the units by the cost per equivalent unit. The same is also done for conversion cost. The conversion cost is the addition of labor and overhead costs.