Answer:
C. $148,350
Explanation:
Actual Overhead $143,350
Less: Underapplied Overhead $18,220
Total Overhead applied $125,130
Actual Direct labor hours = 9700 hours
Overhead rate = Total Overhead applied / Actual Direct labor hours
Overhead rate = $125,130 / 9700 hours
Overhead rate = $12.90 per hour
Estimated Direct Labor hours = 11,500 hours
Estimated Manufacturing Overhead at the beginning = Estimated Direct Labor hours * Overhead rate
Estimated Manufacturing Overhead at the beginning = 11,500 hours * $12.90 per hour
Estimated Manufacturing Overhead at the beginning = $148,350