Project C: What is the total crash cost for crashing the following project by FOUR days? Activity Immediate Normal Time Crash Time Normal Cost Crash Cost CC in $ 8000 7000 Predecessor NT in days CT in days NC in 7000 5000 9000 | A. D B,C 5000 3000 2000 4000 5000 E,F 7000 a. $4000 b. $1500 c. $3000 d. $2500