Answer:
1. Budgeted direct labor cost = Average wage rate for direct labor * Budgeted direct labor hours
Budgeted direct labor cost = $30 * 23,000
Budgeted direct labor cost = $690,000
Overhead rate = Budgeted overhead costs/Budgeted direct labor cost
Overhead rate = $345,000 / $690,000
Overhead rate = 0.5
Overhead rate = 50%
2. Applied Overhead = Direct labor cost * Overhead rate
Job 39 Job 40 Job 41 Job 42
Beginning balance $26,200 $32,800 $16,700 $0
Material requisitioned $18,000 $21,000 $8,400 $13,300
Direct labor cost $9,100 $18,100 $3,050 $4,200
Applied Overhead $4,550 $9,050 $1,525 $2,100
Total Cost $57,850 $80,950 $29,675 $19,600
3. Budgeted direct labor cost = Average wage rate for direct labor * Budgeted direct labor hours
Budgeted direct labor cost = $20 * 23,000
Budgeted direct labor cost = $460,000
Overhead rate = Budgeted overhead costs/Budgeted direct labor cost
Overhead rate = $345,000 / $460,000
Overhead rate = 0.75
Overhead rate = 75%