Answer:
$16,200 favorable
Explanation:
The computation of the total controllable cost variance is shown below:
= Budgeted overhead - actual overhead
= (40,000 units × $3.80 + $74,000) - $209,800
= ($152,000 + $74,000) - $209,800
= $226,000 - $209,800
= $16,200 favorable
Hence, the total controllable cost variance is $16,200 favorable