As a project manager, you review your budget and notice one vendor is costing more than anticipated. You shift funds and recalibrate the budget to offset this increased vendor cost. What is the budgeting term for this task?
A. Contingency budgeting
B. Reserve analysis
C. Setting the baseline
D. Reforecasting